The PGCA (Palm Greens Community Association) keeps us updated on the development of Delray Trails and is our liaison to Lennar.
Lennar and Palm Greens Community Association Board of Directors Update, January 2024
POD A
- Sales continue to grow, will get an update on the total sold in the next day or two
- New homes are going up just about everyday
POD B
- Sales continue to grow, will get an update on the total sold in the next day or two
- Expecting owners to begin taking possession of units in the March/April time frame
- The piles of “clean” dirt on the south end will begin to be moved to POD C in the next 30 to 60 days
POD C
- Earth work continues
- Attaining all the permits to begin vertical construction
- No timing when they expect vertical construction to begin
Clubhouse
- Building footings have been installed
- Expecting to begin erection of walls in the next few days
- Drive over to the Rec Association west parking lot and look north to see the construction activity
Palm Greens Community Association Board of Directors
Lennar and Palm Greens Community Association Board of Directors Update, December 2023
Progress Lennar has the building permit in hand.
The PGCA received a message at 2:09pm today from Dave Povio Lennar’s Amenities Manager that the county has approved the permit for construction of the New Clubhouse. See confirmation below. This great news for Condo 1, Condo 2 and Delray Trails. Construction is estimated to take 18 to 24 months.
Work began earlier this week in the area of the future clubhouse.
markers for the footings for the building.
Here are highlights from our November 2023 meeting with Lennar
POD A
- Construction continues on schedule
- Expecting first occupancies end of November
- 3 models are now open
- 45 homes have been sold
POD B
- Construction continues on schedule
- Estimating first occupancies in March/April 2024
- 29 townhomes have been sold
- Dirt piles at south end to disappear in the next few weeks
POD C
- Breaking ground in the next 30 days
- Units to be the same a POD B
- There will be 84 units
Clubhouse
- All County Departments have signed off. There is one last task for Lennar which is to place the orange fencing around trees in the Recreation Campus area. Once that is done the permit will be approved
Other
- Work on the walking path around Water Tracts 1,2 and 3 has begun
- Once the path is complete final landscaping will begin
Palm Greens Community Association Board of Directors
Here are highlights from the October 15 meeting with Lennar
POD A
- Construction continues on schedule
- Expecting first occupancies end of November
POD B
- Construction continues on schedule
- Estimating first occupancies in March/April 2024
POD C
- Permits being submitted
- Bids in process
- No date for breaking ground on buildings
Clubhouse
- No permit at this time
- Application as of October 11, in process for 141 days
- The County’s latest question from zoning and landscaping has been answered.
- Lennar manager in charge of the building of the clubhouse described approval as being very close
- Courts 4,5,6.- Lennar has indicated that the refurbishment of the courts will be completed by the end of October.
- New fencing is in the warehouse
- Additional Har Tru is in transit
Other
- Work on the walking path around Water Tracts 1,2 and 3 has begun
- Once the path is complete final landscaping will begin
Palm Greens Community Association Board of Directors
From Condo 2 Court H1 – View of POD A homes
Highlights from the Latest Monthly Meeting with Lennar (Mid-September 2023)
POD A
- Construction continues on schedule (see pictures)
- Expecting first occupancies in November
POD B
- Construction continues on schedule
- First two buildings taking shape (see picture)
POD C
- Not much activity. Focus is on PODs A and B
Clubhouse
- No permit at this time
- Application as of September 13, in process for 111 days
- County came back on August 10 with comments and then again on August 18. The County wants answers grouped together so Lennar waits for at least a week to see if there are additional comments and then responds.
- Lennar has done as much prep work that they can without a permit.
- Lennar is very frustrated that it is taking this long.
- Courts 4,5,6.- Lennar has indicated that the refurbishment of the courts will start the weekend of September 23 and will be completed by the last weekend of October.
- Tennis courts footnote – there is only one mine in North America that produces the Har-Tru surface material. It is located in the Blue Ridge Mountains of Virginia. Demand for their product is huge.
- Below of photos from the updated Lennar Project:
POD A Main Entrance
POD A New Roads Being Created
POD B – New Structures and in the background new roof trusses crane as well as new foundation being poured via boom arm.
Highlights from the Latest Monthly Meeting with Lennar (Mid-August 2023)
POD A
- A section of road has been paved.
- Additional paving to take place in the next few weeks.
- Additional paving in the mid-September timeframe
POD B
- Forms being built for foundations to be poured.
- Estimated occupancy of first units January 2024
POD C
- Lot sizes similar to POD B with townhomes
- No prediction on permit timing
Clubhouse
- No permit yet, hopefully by the end of August
- The county indicates there are multiple other projects in the works to be permitted.
Other
- Due to new storm drains being installed for the new clubhouse the old irrigation line was damaged. Lennar will lay a new pipe in accordance with the plan for the new clubhouse (see picture in the Courts 4, 5, 6 area). Then the refurbishment of the courts will begin.
- The walking path construction per the plan around Water Tracts 1,2 and 3 is to start soon.
- Once the path is complete the landscaping work will be completed.
PGCA – July 12, 2023 – Highlights from the Monthly Meeting with Lennar
POD A
- 25 Single Family Homes sold to date
- As stated previously first Certificates of Occupancy expected in November
- There are at least 25 homes with roofs and approximately 15 or more in various stages from foundations poured to awaiting roofing structure
POD B
- 15 TownHomes sold to date
- Expecting permits to start TownHome construction “Soon”
POD C
- Property has been purchased by Lennar
- Unit density will be less than in the Development Agreement, which is in compliance with the agreement.
Clubhouse
- Anxiously awaiting the permit from the county
- The new building site has been prepared and staked out
- Onsite construction meetings taking place
Other
- Lennar is hiring a company to trim the weeds and grass around their entire property. and that work is to begin shortly. Please be patient
- Discussions taking place to potentially pull the refurbishment of the existing tennis court ahead to the late summer, early fall of this year.
See below for the POD A Construction Photos